Signed in as:
filler@godaddy.com
Signed in as:
filler@godaddy.com
Our 5 year Dam Safety Inspection was performed in Fall 2023 and the periodic inspection report by the Dam Safety Office was received in 2025. There were 5 observations and the overall rating of POOR condition for the dam, in addition to the past observations from the 2018 inspection that we are still working on. In May 2025, a Dam Maintenance plan was developed and agreed upon with Dam Safety and progress is discussed at board meetings.
A lot of headway has been made, vegetation clearing and now maintaining those cleared areas on and around the Dam, canal and weir areas. Installing staff gauges to monitor lake water levels. We perform an annual owner inspection in the fall and file the report with DSO, along with updates to the Emergency Action Plan and the Operations and Maintenance Plan every year. Many discussions have taken place with DSO staff on remediation for the Seismic evaluation as well as the emergency outlet system where preliminary bids for the plan on replacement have been obtained. DSO has been kept up to date with our progress and the team continues to manage and discuss the activities still needing attention. Board Members are actively pursuing the remaining items.
Our second grant application for a High Hazard Dam Grant was approved by FEMA in fall 2025... we are partnered with King County to manage the dam grant for the seismic and stability evaluation of the dam and we have identified a local geotechnical contractor to work with. The federal grant will require the community to pay a 35% portion with the federal grant funding at 65% of the original application amount from 2024.
We had hoped to apply for a second FEMA grant for funding assistance to cover the emergency outlet replacement project and the filling of the low spots along the canal. These projects will require us to have several contractor bids as well as filing for an additional hydraulic permit. Unfortunately, we do not have a clear path forward on FEMA or grant opportunities at this time.
Andy Quast worked on the grant application, Molly Graham obtained updated bids and helped with grant review, Kacie Ciske handled the hydraulic permits from the Dept of Fish & Wildlife for maintaining the beaver dam in the outlet canal. Tom Morgan and Molly Graham worked on finalizing the vegetation clearing and meeting with various contractors onsite. The initial seismic bids were gathered in 2011 by Arnold Pretz . All board members are active and the team includes community members George Edwards, Laura Gunion and Doug Linman.
Contact a board member if you are interested in participating, or would like more details or information about the project. We always need your assistance !
Kayak Lake Dam Emergency Action Plan 11-2022 (pdf)
Download
Brush Mowing was performed in Fall 2019 on the steep back side of the main dam

Manual brush clearing was performed on the back side starting at the corner where the main dam meets the canal in late June 2021

Regular clearing and mowing 'maintenance' is being performed to keep all cleared areas accessible and easily inspected. Includes dead tree removal for the main dam and canal for the entire back side, top and front down to the waters edge.



Add a footnote if this applies to your business

Beaver activity in the canal, blocking the outlet channel

Beaver dam upstream from the weir

Gotta keep those teeth sharp!